Description
Based on findings from AARC and REFEDS, pilot and implement the recommendations on the Security Incident Response Trust Framework for Federated Identity (SIRTFI) in the eduGAIN operational context.
1.4 | eduGAIN Incident Management platform integration | ||||
1.4.1 | Design Phase | ||||
Identify impact on eduGAIN central infrastructure e.g. EC monitoring reqs, audit reqs. | M1 | T0 Brook | |||
Prepare BCP for adoption of Sirtfi by Good eduGAIN Citizens | M12 | Provide provisional suggestions first then use surfnet & switch pilots to provide final | |||
Update eduGAIN CBA | T0 Brook | ||||
Design Tooling | M18 | Check federation experience first | |||
1.4.2 | Pilot | M1-M18 | We may want to split piloting central support and NREN takeup | ||
Support takeup by NRENs | Ongoing | ||||
M9.4 SIRTFI Pilot Report | EC Milestone | M20 | |||
1.4.3 | Transition to production | M18-M20 | Need to define what production means for this since implementation is not our scope |
Current Status
Milestone/Deliverable
GREY Milestone M9.4: SIRTFI Pilot Report, M20, Report