Work in progress!!!!
Provide some context for the transition. What is in place now, what is rough timeline for service: for example reach pilot by time a, run pilot for period p and based on results run the service in production by time c. Give some view on what happens with the technical infrastructure through this - i.e the installation will remain ... Example from managed idp transition bellow:
Relation to pilot The pilot is running on testing-level virtual machines (Okeanos). A continuation on those VMs is not foreseen. The production system is an installation "from scratch". Accounts created in the pilot installation remain valid until their expiry, or 01 Dec 2018 (whichever comes FIRST; expiry date of intermediate CA). For the RADIUS authentication of these pilot-phase accounts, there are two options:
We have to keep the management UI and the OCSP responder online until 01 Dec 2018 so that activities such as revocation are still possible. However, pilot-phase IdP administrators should not create new accounts on the pilot system when the production one is available. |
The transition generally consist of the following areas of work:
- Documentation preparation and signoff
- Test and Validation
- GDPR compliance checking
- IPR compliance checking
- Operational team establishment
- Operational team training
- Support team establishment
- Support team training
- Operational deployment
- Service promotion
Define the people involved:
Teams/people:
- Service Owner: Christos Kanellopoulos
- Governance engagement: Klaas Wierenga
- Development team: Leif Johhanson, Fresia Perez Arriagada, Elena Rakhimova
- Operations team: Erik Bergstörm, Maria Haide (Sunet)
- GEANT T&I operation support/Core team: Nicole Harris
- PLM product manager: Not applicable at the moment being this a joint effort between GN4-3/GEANT, Internet2 and the RA21 initiative.
- Test team: ?
- IPR: Magdalena Rzaca
- GDPR: Magdalena Rzaca GEANT GDPR team
ON HOLD
IN PROGRESS
DONE
No | Work item | Responsible | Comment | Status | Start date | End date |
---|---|---|---|---|---|---|
1 | Preparation of documentation | |||||
Service Description | -Development team prepares -SO signs off | RA21 Discovery Service Description | ||||
Service policy (Terms of use, SLA) | -Development team prepares -SO signs off | Separte policies for NROs, eduroam Managed IdP administrators and end users are described at eduroam Managed IdP Service Policy. Terms of use for NRO admins is published at: Terms of use for IdPs and end users is presented in the web UI of the service, and also at: | ||||
Branding and Visibility | -Development team prepares -SO signs off | Web page text at https://www.eduroam.org/eduroam-managed-idp/ | ||||
Operational Requirements | -Development team prepares -SO signs off | RA21 Discovery Operational Requirements | ||||
OLA | -Development team prepares -SO and GEANT T&I operation support/Core team sign off | eduroam Managed IdP OLA | ||||
Operational documentation | -Development team prepares -SO signs off | Dev team prepared this in the corresponding Wiki page | ||||
Operational processes | -Development team prepares -SO signs off | Need to define: service order (what happens from point of interest to service availability for a customer) and support process. Marina sent the questionnaire prepared by the Task 4 to Stefan to provide the info and Task 4 can draw the flow charts. The questionnaire is here. Not required for production sign-off. | ||||
User documentation | -Development team prepares -SO signs off | |||||
User support | -Development team prepares -SO signs off | Prepare the FAQ for the first level support. List is available here. Add them to the current FAQ that service desk uses + enable service desk to check by themselves if a user's IdP is managed eduroam IdP | ||||
GDPR - data inventory, privacy notice, DPA | -Development team prepares -GDPR accountable and SM signs off | The main eduroam privacy notice was updated. Signed off by the GDPR team on 26th of November 2018. Needs to be published in the eduroam site after the official launch. DPA will be done together with the eduroam service DPA. | ||||
2 | Test and validation | |||||
Make a test plan | Development team and Test team prepares | Testing of the code was done when new version of CAT v2.0 was tested as there use the same code base - no critical issues. The testing of the UI and usability was also done. There are no bugs, recommendations for UI improvements were implemented by the Development team. Pen testing done - no critical issues. | ||||
3 | IPR compliance checking | |||||
IPR compliance | IPR accountable Route the request through GEANT T&I operation support/Core team | Stefan Winter prepared the IPR request (what are the software components, libraries, tools used) on this page. Alan confirmed Shaun has approved on 06.11.18 Documentation: eduroam Managed IdP - IPR | ||||
4 | GDPR compliance checking | GDPR accountable | ||||
Data inventory and mapping | Data inventory is already prepared; with Nicole and Ana to carry out assessment | |||||
Update the privacy notice and DPA | Look at the 1 - GDPR | |||||
5 | Operational team establishment | |||||
Appoint service owner | WP5 leaders | It comes under the eduroam service family and existing service manager. | ||||
Define roles, skills, manpower needed | Development team | As per current team for the skills, but additional time would be needed. | ||||
Appoint operational team members | Service Owner | |||||
6 | Operational team training | |||||
Training the operational team | Not needed. | |||||
7 | Support team establishment | |||||
Establish the support team | Level 1 done by the GEANT Service Desk, L2 will be over the eduroam-ot, L3 will be via the development team Note: After PLM enter production gate, SM to notify L1 that the service production started | |||||
8 | Support team training | |||||
Training of the support team | Not needed. | |||||
9 | Deployment in production environment | |||||
Monitoring set up | Operations team based on the requirements from the development team SO signs off when implemented | Provided by SRCE as part of the eduroam-OT | ||||
Back-up and restore | Operations team based on the requirements from the development team SO signs off when implemented | VM snapshots are backed up by GEANT IT as defined in the GÉANT PoP Backup policy. Daily database snapshots are additionally kept at monitor.eduroam.org host. Perform a smoke test to test the restore process as a whole!! The idea is to take a machine down and ask GEANT IT to restore. Dick Visser is leading. OCSB machine is the best candidate. | ||||
VM provision | Operations team based on the requirements from the development team SO signs off when implemented | GEANT IT VMs | ||||
Installation of the components | Operations team based on the requirements from the development team SO signs off when implemented | Stefan, Tomasz, Maja SMS service has been ordered and awaiting payment of bank transfer by GÉANT. | ||||
CDN | ? | GEANT T&I operation support/Core team: can organise the root CA creation ceremony, and safe offline storing of the Raspberry PI (in a safe). Dick Visser will see if there is a safe in the GEANT AMS office. If not, SA2 can purchase one. In eduroam IdP Operational Processes page there is detail on setting up the CA. | ||||
10 | Service Promotion | |||||
Web site update | Karl and Justin | Prepare all in the eduroam PR site, but publish when the production gate is passed. Web page draft at https://www.eduroam.org/eduroam-managed-idp/ Marina Adomeit, Miro and Karl prepared the final version only waiting to be published. | ||||
Add the service to the partner services portfolio | Justin | Added to the partner portal. In staging area ready to go live when service goes into production. | ||||
Contact the people/NRENs who took part in the infoshare to update them on service availability | Partner Relations | Two communications: First to the participants who joined the infoshare to say that the gate is passed and service is coming Second upon launch to the GEANT partner list. | ||||
Update eduroam flyer with the managed service element | Silvie | |||||
Slide deck from the infoshares that can be sent out by Partner Relations to partner NRENs when service is live | Justin | Available | ||||
Training/info video to put on the website | Karl | Lower priority; not needed for production. | ||||
Article for CONNECT | Justin and Karl | Went into October CONNECT | ||||
Launch announcement in Tryfon's weekly email when reached | Justin and Tryfon | Arranged with Karl and Nathalie 10.12.18. Karl will prepare text, Marina to confirm when gate approved. | ||||
Twitter #love2eduroam upon launch | Karl | Not required for production gate. | ||||
Promotion via the eduroam-SG, by the service manager | Miro | Miro has let the SG know to expect this. There are meetings in November and December. | ||||
A slide describing the service for the partner relations team (as part of the general GEANT services slide deck) | Karl | |||||
Decision about the geographical scope of the service offer - who can use the service | Klaas | Klaas confirmed 10.09.18 that the service can be offered to non-GEANT partners. The user cap of 10,000 will apply to all. | ||||
11 | PLM Documentation | |||||
CBA update Costs and funding excel Roadmap | Justin Knight | CBA, costs and funding sheet, and roadmap all updated and put on JRA3 PLM staging site. Alan Lewis has reviewed and is content. JRA3 PLM Staging Area#emidp-production-gate-documents Marina Adomeit will, after the PLM gate, move the documentation from the JRA3 PLM staging site to the eduroam wiki pages. |