EC project review (including deadlines): we want to have a first version of the whitepaper ready by then (25 March either 1pm or 1:45pm, rehearsal 6th of Feb)
no big deal, we basically could present out task list with names and some insights into the
TNC: under review to have a physical T7 meeting → we prefer a physical meeting outside of TNC
Next additional meeting in one week's time (because of attendance problems one week later)
Action items
Action
Who
Deadline
Status
Prepare a draft TOC for the report and check for project dependencies
Christoph (check with Marina)
asap
open
apply for items in the list of activities, include your estimated efforts you're willing to contribute → will be done in separate per WI calls in the weeks after 22nd Jan
all
end of Jan '24
open
Check options for TNC 24 side meeting for T7
Christoph
calendar of TNC
closed / won't do
Issue call for a physical T7 meeting in April/ early May
Christoph
end of Jan 24
open
propose lightning talk on "the whitepaper" or to cover the "new kid on the block"
any one from our group
calendar of TNC (early Feb?)
open
additional meeting in one week's time
Christoph
asap
done
Backlog
Review existing services to identify opportunities and challenges to adopt the distributed technologies paradigm. Grab existing results as a start
Gather previous work done by the NRENs/universities on using SSI technologies, as well as other sectors. Crowd-source among ourselves