1.4 | eduGAIN Incident Management Platform Integration | Type | Month | Responsible | Comments | ||
---|---|---|---|---|---|---|---|
1.4.1 | Design Phase | ||||||
Requirements Gathering: eduGAIN central role | M1 | T0 | Thomas B Nicole Pal | Definition of basis function as both initial support and future requirements. . | |||
BCP: Sirtfi in eduGAIN | M12 | Nicole | Provide provisional suggestions first then use surfnet & switch pilots to provide final. Delayed due to issues finalising the SAML Profile. | ||||
Incident Response Framework Template for Federations | TBA. | New proposal suggested required by Nicole. See the InCommon example. | |||||
Update eduGAIN CBA | T0 | Justin?? | Not sure what this was supposed to be? | ||||
Design Tooling | M18 | ?? | Check federation experience first | ||||
1.4.2 | Pilot | M1-M18 | We may want to split piloting central support and NREN takeuptake-up | ||||
Support takeup by NRENs | Ongoing | AARC are sending test cases so this is being piloted whether we want to or not. | |||||
M9.4 SIRTFI Pilot Report | EC Milestone | M20 | |||||
1.4.3 | Transition to production | M18-M20 | Need to define what production means for this since implementation is not our scope |
...