Goals

...

TimeItemWhoNotes

Firewall On Demand (FoD)
  • Evangelos setup VC with UAT pilot users, 11.12.2017, 12:00 CET
  • VC will have to be setup to investigate current NETCONF connections issues with test machines in lab

Certificate Transparency (CT)

Open Points

Next VC

In 2 weeks: 13.12.2017, 14:15-15:15 CE(S)T

Action items

  •  Evangelos: again review UAT FoD
  •  David/Evangelos: update of user documentation presentation for FoD v1.5
  •  David/Evangelos: review/update existing pilot evaluation survey
  •  Evangelos: check the FoD service template (https://wiki.geant.org/display/gn42jra2/Firewall-On-Demand+%28FoD%29+Service) to get acquainted with it
  •  Silvia/Nino: report progress on GARR DDoS D/M PoC
  •  all: Next regular T6 VC: 13.12.2017, 14:15-15:15 CE(S)T

...