In GN4-2 JRA3 is responsible for further development of eduroam service. The roadmap was discussed during the Project Management Convention, resulting in the following: 

  • eduroam as a service - eaas - detailed roadmap 
    • Overall system design specified – DONE
    • Implement first prototype – ONGOING
    • finalize first prototype for the service – Dec 2016 [COMMITED]
    • launch pilot for the service – Jan 2017 [COMMITED]
          -> functional except credential revocation; preliminary UI; see “Pilot Features”
    • stop the pilot – May 2017 [PLANNED]
    • eaas beta version – June 2017 [PLANNED]
          -> fully functional, near-final UIs; see “Beta Features”
    • eaas v1.0 – July 2017 [PLANNED]
    • documentation and acceptance testing – Sep 2017 [POSSIBILITY]
    • service launch and handover to production – Oct 2017 [POSSIBILITY]
  • eduroam user diagnostics
    • analyse requirements - Dec 2016
    • start development - Jan 2017
    • finalize prototype - June 2017
    • early adopters release and acceptance testing- July 2017
    • service launch - Oct 2017
  • radsec scalability
  • CAT development

Service availability and incidents

...