Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


This page contains information about roadmap for devops, but may include description to actual issues and developments.

RESPONSIBLE: Content is defined and maintained by devops team.

 

eduroam devops team is responsible for operating and managing operational side of eduroam. Devops roadmap notes any outstanding activities from the "business as usual". Business as usual implies:

  • technical part: maintain and when needed adjust configurations and resolve user reported problems for:
  • organisational part
    • provide content for www.eduroam.org + eduroam wiki
    • organise eduroam SG meetings
    • liaise with GeGC
    • liaise with JRA3
    • expert level support for user questions received

 

ActionDescriptionPriority (1-lowest, 5-highest)StatusDue DateAssigned toComment
NRO audit - first
eduroam DB ver 2

public draft spec released

NRO audit is a new measure of evaluating the practices of National Roaming Operators against the mandatory and recommended requirements defined in the eduroam policy. The aim is to gain knowledge of how well NROs are aligned with eduroam policy. The ones who are not following the mandatory requirements will be urged to do so. The ones who are not following the recommended requirements will be motivated to do that in greater measure.
 
Status
colour
YellowNRO audit -
Green
title
iN pROGRESSJan 2017  
FINISHED
2016.06 (June) eduroam DB ver 2 is revised version of database that
holds information about NROs, IdPs, Service Locations etc
eduroam DB ver 2
final spec released 
Status
colour
Grey
Yellow
title
nOT STARTEDMar 2017
IN PROGRESS
2016.12 (Dec)  

NRO audit

-

first draft spec released

first audit run

 
Status
colour
Grey
Yellow
title
nOT STARTED
iN pROGRESS
May 2017 
2017.01 (Jan) NRO audit
-
is the process of evaluation of the NROs against the
requirements defined in the eduroam policy.
The aim is to gain knowledge of how well NROs are aligned with
eduroam policy and help them to improve the level of the service.
eduroam DB ver 2SW
audit report
released 
Status
colour
Grey
Yellow
title
nOT STARTED
IN PROGRESS
June
2017.01 (Jan)  
NRO audit
-
final spec
update
released 
Status
colourGrey
titlenOT STARTED
2017.03 (Mar
2018
)  
eduroam DB ver 2uptake review
NRO audit - second audit run
 
Status
colour
Grey
title
nOT
NOT STARTED
2017.05 (May
2018
)  
eduroam DB ver 2 - public draft spec released
NRO auditfirst audit run
 
 
Status
colour
Green
Grey
title
fINISHED
nOT STARTED
2017.05 (May)
June 2016
  
eduroam DB ver 2 - final spec released 
NRO auditaudit report released 
Status
colour
Yellow
Grey
title
iN pROGRESSDec 2016
nOT STARTED
2017.06 (June)  
eduroam DB ver 2
- SW released 
close ver 1.0 support 
Status
colourGrey
title
nOT
NOT STARTED
2018.01 (Jan
2017
)  
eduroam DB ver 2 - uptake review 
NRO auditspec update released 
Status
colourGrey
titlenOT STARTED
May 2017
2018.03 (Mar)  
eduroam DB ver 2 - close ver 1.0 support 
NRO auditsecond audit run 
Status
colourGrey
titlenOT STARTED
Jan
2018.05 (May)  

 

Examples for status codes:

...