1-270917 Peter to distribute the agreed OKR document to all Up2U project partners. Define the main focus of the project's expected impact.Deadline ASAP.
2-270917 Urge the technical work packages to start piloting with alternative LMS platforms (OepnEdXOpenEdX, Canvas). Peter to organize an Architecture Review Meeting.ASAP.
3-270917 Organize virtual all-hands meeting in the next coming two weeks and encourage the work package leaders to organize face-to-face technical meetings to solve the critical issues.In two weeks.
4-270917 Peter to follow up with partners who are deviating from the linear financial progress and ask for clarifications.Deadline next Board meeting and/or Q3 report.
5-270917 Peter to distribute the agreed new budget table and ask for further modification requests to be implemented in the next round.Deadline ASAP.

...