...
No | Work item | Responsible | Comment | Status | Start date | End date | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Preparation of documentation | |||||||||||
Service Description | -Development team prepares -SO signs off | Need to prepare high level service description | DONE Stefan Winter to review documentation from the pilot and update if needed - SW: Updated | |||||||||
Service policy (Terms of use, SLA) | -Development team prepares -SO signs off | Write at the UI that this is pilot and there is no SLA guaranteed. | do we promise something for production? | |||||||||
Branding and Visibility | -Development team prepares -SO signs off | we want to co brand it to eduroam hosted services | need to go through the branding and sites to make the changes | |||||||||
Operational Requirements | -Development team prepares -SO signs off | We should document what are ops requirements for running pilot (see eduroam managed SP Operational Requirements) | Paul Dekkers Stefan Winter to update - SW: Updated | |||||||||
OLA | -Development team prepares -SO and GEANT T&I operation support/Core team sign off | not relevant for pilot (example for production later eduroam Managed IdP OLA) | Paul Dekkers Stefan Winter have a look to existing one and try to make it eduroam Hosted services. | |||||||||
Operational documentation | -Development team prepares -SM signs off, test team can validate | Tomasz and Maja through eduroam-OT are the ops team. Documentation not relevant for pilot ( example for production later Dev team prepared this in the corresponding Wiki page) | ||||||||||
Operational processes | -Development team prepares -SM signs off, test team can validate | not relevant Service order is done through the UI Service support is the same like for eduroam supporting services. | ||||||||||
User documentation | -Development team prepares -SM signs off, test team can validate | DONE Stefan Winter to update - SW: Updated | ||||||||||
User support | -Development team prepares -SM signs off, test team can validate | We dont need anything special for pilot as we will work with a defined group of pilot participants directly | ||||||||||
GDPR - data inventory, privacy notice, DPA | -Development team prepares -SO and T&I service portfolio reviews -GDPR accountable signs off | eduroam privacy notice was updated to reflect the changes of eduroam managed SP, and was approved by GEANT DPO eduroam Privacy Notice - Changes for Managed SP | | |||||||||
2 | Test and validation | |||||||||||
Make a test plan | Development team and Test team prepares | We dont need to do code review for the pilot, but it is a good idea to do test the code during the pilot, as preparation for production Stefan Winter initiated the scans with Marcin Wolski . It was agreed to do the code scan in second half of 2021 | DONE | |||||||||
3 | IPR compliance checking | |||||||||||
IPR compliance | IPR accountable Route the request through GEANT T&I operation support/Core team | White source review was done by the WP9 team Results are available to WP9 team, WP5 lead and eduroam team and to GEANT IPR person https://app-eu.whitesourcesoftware.com/Wss/WSS.html#!product;id=78288 Based on the results, GEANT IPR has signed off the IPR compliance check. |
| |||||||||
4 | GDPR compliance checking | GDPR accountable | ||||||||||
Data inventory and mapping | Data inventory and mapping were updated | was done for the pilot, check the policy. same considerations as for the radius proxies Marina Adomeit | ||||||||||
Update the privacy notice and DPA | eduroam privacy notice was updated to reflect the changes of eduroam managed SP, and was approved by GEANT DPO eduroam Privacy Notice - Changes for Managed SP | DONE - check it but it shoudl have been done Marina Adomeit | ||||||||||
5 | Operational team establishment | |||||||||||
Appoint service manager | Operations accountable | It comes under the eduroam service family and existing service owner. Paul Dekkers | DONE | |||||||||
Define roles, skills, manpower needed | Development team | production will be supported by the eduroam-OT and dev team | DONE | |||||||||
Appoint operational team members | SM | Maja and Tomasz. Paul will check if they want to continue. Srce maintains the Ops system | ||||||||||
6 | Operational team training | |||||||||||
Training the operational team | Development team prepares eduroam-OT is trained | Not needed. |
| |||||||||
7 | Support team establishment | |||||||||||
Establish the support team | Pilot doesn't need dedicated support team - dev team will work with limited pilot participants | |||||||||||
8 | Support team training | |||||||||||
Training of the support team | Development team prepares eduroam-OT is trained | Not needed. | ||||||||||
9 | Deployment in production | |||||||||||
Monitoring set up | eduroam-OT | Done by SRCE. There is one monitoring port that is set up. | double check with dragan if it is in place | |||||||||
Back-up and restore | eduroam-OT | done with the same tools like for cat, encrypts and sends to AWS | double check with dragan if it is in place | |||||||||
VM provision | GEANT T&I operation support/Core team | Production - GEANT VM is not the most reliable. We need to add another at another place Amazon or an NREN such as SURF to be determined. | ||||||||||
Installation of the components | eduroam-OT | Stefan, Tomasz, Maja Radius servers will need to be deployed in the second location. | ||||||||||
10 | Service Promotion | |||||||||||
Web site update | Need to change the branding to the eduroam hosted service. Add it under eduroam tools remove the page https://eduroam.org/eduroam-managed-idp/ and adapt it to hosted tools |
| ||||||||||
Add the service to the partner services portfolio | check if we need this kind of granularity | |||||||||||
Contact the people/NRENs who took part in the infoshare to update them on service availability | ||||||||||||
Update eduroam flyer with the managed service element | ||||||||||||
Slide deck for Partner Relations | SO | |||||||||||
Article for CONNECT | ||||||||||||
Launch announcement in Tryfon's weekly email when reached | SO/Development team | |||||||||||
Write géant blog | SO/Development team | |||||||||||
Webinar / infoshare | ||||||||||||
Promotion via the eduroam-SG, by the service manager | SO | |||||||||||
11 | PLM Documentation | |||||||||||
CBA | Development team and T&I service portfolio guardians | Marina Adomeit to check if there is template | Marina Adomeit to update for production |
...