Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

KPI

Baseline  
(start of GN5-1)

Target 

  (end of GN5-1)

Measured

P1 reporting period

Jan 2023-June 2023

Measured

P2 reporting period

July 2023-December 2023

Comments

Metadata Service (MDS) availability

99.5%

99.5%

100%
Uptime calculated monthly, the reported value is the lowest. See eduGAIN Service Status page for details: eduGAIN Services Status

% of all SAML2 identity federations that are members of eduGAIN 

In 2021: 4667

In 2022: 5235

8% increase for the GN5-1 project duration

5390

(+2.95%)


Calculated as the number of eduGAIN full members against the R&E federations known by REFEDS at the end of the reporting period, see https://refeds.org/federations


GEANT

...

AAI Service KPIs

KPI

Baseline  
(start of GN5-1)

Target 

  (end of GN5-1)

Measured

P1 reporting period

Jan 2023-June 2023

Measured

P2 reporting period

July 2023-December 2023

Comments

GÉANT SP Proxy Service availability

99.5%

99.5%




GÉANT SP Proxy Service Connected Service

-

100 at the end of the GN5-1 project




...